Hanoi addresses bottlenecks in Ring road No.4 project

9:57 PM, Mon December 16, 2024

Politburo member and Secretary of the Hanoi Party Committee, Bui Thi Minh Hoai has urged localities and agencies to continue cooperating and addressing emerging challenges proactively to ensure progress.

Politburo member and Secretary of the Hanoi Party Committee, Bui Thi Minh Hoai, on December 12 chaired a meeting to review progress, assess the current situation, and address challenges and obstacles in the project's execution. Solutions to accelerate the project's progress were also discussed.

Regarding land clearance progress in Hanoi, 786.2 hectares out of 798.65 hectares have been cleared, accounting for 98.44%, with 12.45 hectares remaining. This includes 2.93 hectares of agricultural land and 9.52 hectares of residential land. Additionally, land clearance for 5.73 hectares out of 9.96 hectares has been completed, and 34 of 36 high-voltage pylon foundation sites have been cleared. A total of 10,281 graves out of 10,347 have been relocated, or 99.36%. To date, 776.82 hectares have been handed over, covering 48.35 km of the total 52.73 km, or 91.7% of the project length.

Bí thư Thành ủy Hà Nội Bùi Thị Minh Hoài phát biểu tại Hội nghị

Overview of the meeting. 

Hanoi has also made significant progress in resettlement, with housing provided for 337 out of 818 households. The land pricing for expropriation has been mostly approved in all districts, except for Dan Phuong District. The Hanoi People's Committee has directed the Department of Natural Resources and Environment to address the sequencing of land clearance, resettlement land allocation, and land pricing issues. The aim is to finalize land clearance and hand over all land by December 31, 2024, with some particularly challenging cases expected to be completed before the Lunar New Year.

Regarding the adjustment to Component 1.1, the Department of Transport has submitted a proposal to extend the implementation deadline to the end of Q2 2025, with land clearance and infrastructure relocation set to be completed by Q1 2025.

As for the funding allocated to Hanoi, VND14.3 trillion ($595 million) has been allocated, with VND10 trillion ($420 million) already disbursed, representing 71.81% of the total. In 2024, VND1.5 trillion ($63 million) has been disbursed out of the planned VND3.7 trillion ($150 million), or 41.68% of the target.

For the construction projects, Component 2.1 has seen four construction packages launched along 48.35 km of the route, with 32 active work fronts (23 for roads and 9 for bridges). The project is on track to be completed in Q4 2025. For Component 3, the public investment sub-project under the PPP model, surveys and technical designs have been ongoing from February to May 2024. 

By August 2024, the Vietnam Highways Directorate approved the detailed design. Regarding the overall investment adjustment, the total estimated cost for all seven components is expected to be reduced by about VND2.34 trillion ($95 million) from the initial estimates in Resolution No. 56/2022/QH15.

Regarding materials, for the embankment of Component 2.1, over 2.1 million m3 of sand (about 85% of the required volume) has been sourced from commercial suppliers and special quarries, ensuring sufficient supply. As for embankment soil, approximately 0.765 million m3 (about 65% of the required volume) has been gathered. The remaining volume will be sourced from excess material in Hoa Binh Province's quarries, with gravel aggregates being supplied from nearby quarries.

Component 3 is expected to begin construction by Q2 2025.

In her closing remarks, Hoai, who is also the head of the Steering Committee for the implementation of the Ring Road 4 Project in the Capital Region, acknowledged the substantial progress made, particularly by Hanoi, Hung Yen, and Bac Ninh, in overcoming challenges like land clearance and parallel road construction. 

She urged localities and agencies to continue cooperating and addressing emerging challenges proactively to ensure progress.

She also highlighted the importance of prioritizing the well-being of affected communities, ensuring that all support mechanisms are fully utilized to help those impacted by land clearance. Any issues that arise should be reported promptly, with solutions proposed in line with legal requirements.

The goal is to complete land clearance in all three provinces and cities by the Lunar New Year and to begin construction of Component 3 by Q2 2025. Hanoi's Party Secretary also mentioned that if no investors have joined by January 6, 2025, alternative investment plans should be considered, potentially shifting to public funding.

The Hanoi Ring Road No. 4 project involves the construction of a 113-kilometer highway spanning Hanoi, Hung Yen, and Bac Ninh. Starting from the junction of the Hanoi - Lao Cai Expressway and ending at the Noi Bai - Ha Long Expressway, the project has a total investment of VND55 trillion (around $2.26 billion) and is scheduled for completion by 2027.

Hanoi People's Council holds effective discussion session

16:48 10/07/2025

After a focused, serious, democratic, and highly responsible working session in the morning, the Hanoi People's Council successfully concluded its question-and-answer session during the 25th meeting of its 16th term.

Most views
Same category
Find by date
Hanoi People's Council holds effective discussion session
Hanoi People's Council holds effective discussion session
After a focused, serious, democratic, and highly responsible working session in the morning, the Hanoi People's Council successfully concluded its question-and-answer session during the 25th meeting of its 16th term.
16:48 10/07/2025
Hanoi approves incentive policies for waste recycling activities
Hanoi approves incentive policies for waste recycling activities
During the continuation of the 25th session of the 16th tenure of the Hanoi People's Council on July 10, delegates reviewed and approved a Resolution that sets forth support and incentive measures for waste recycling activities applying the best available techniques within the city. This Resolution was enacted in accordance with Point d, Clause 2, Article 28 of the Capital Law.
16:23 10/07/2025
Hanoi approves policies to support agricultural zones affected by natural disasters
Hanoi approves policies to support agricultural zones affected by natural disasters
The Hanoi People's Council on July 9 passed a resolution establishing agricultural support policies to restore production in areas affected by natural disasters or plant pests within the boundaries of the city.
16:46 09/07/2025
Hanoi to grant land lease exemptions for projects in priority investment sectors
Hanoi to grant land lease exemptions for projects in priority investment sectors
During the 25th session of the Hanoi People's Council (16th tenure) on July 9, council members voted to pass a Resolution introducing policies that exempt land lease payments for projects using land for production and business purposes in sectors or areas classified as investment priorities in Hanoi.
16:46 09/07/2025
Hanoi permits agricultural and tourism use of riverside alluvial land
Hanoi permits agricultural and tourism use of riverside alluvial land
The Hanoi People's Council on July 9 passed a Resolution governing the use and management of agricultural land located on riverbanks and alluvial islets along dike-protected rivers within the city, as stipulated under Point a, Clause 3, Article 32 of the 2024 Capital Law.
16:46 09/07/2025
Hanoi expands eligibility for voluntary social and health insurance support policies
Hanoi expands eligibility for voluntary social and health insurance support policies
The Hanoi People's Council on July 9 approved a resolution detailing the scope and levels of support for voluntary social insurance and health insurance contributions for socially disadvantaged groups residing in the capital.
15:58 09/07/2025
Other news
Hanoi pushes for trade facilitation activities
Hanoi pushes for trade facilitation activities
Vice Chairman of the Hanoi People's Committee Nguyen Manh Quyen on July 10 signed and issued Official Dispatch No. 4023/UBND-DMPT regarding the implementation of Directive No. 18/CT-TTg dated June 18, 2025, by the Prime Minister.
16:23 10/07/2025
Hanoi installs LED screens, loudspeakers for 80th national day celebration
Hanoi installs LED screens, loudspeakers for 80th national day celebration
Vice Chairwoman of the Hanoi People's Committee Vu Thu Ha has signed Decision No. 182/KH-UBND dated July 9, 2025, approving a plan to install LED screens and public loudspeaker systems to serve the Commemoration and Parade celebrating the 80th Anniversary of the August Revolution (August 19, 1945 – August 19, 2025) and the National Day of the Socialist Republic of Vietnam (September 2, 1945 – September 2, 2025) across the city.
16:26 09/07/2025
Hanoi steps up effort to promote science, technologies and innovation
Hanoi steps up effort to promote science, technologies and innovation
Vice Chairman of the Hanoi People's Committee Truong Viet Dung signed Official Dispatch No. 3990/UBND-DMPT on July 8, 2025, regarding the acceleration of implementation of tasks under Plan No. 02-KH/BCDTW dated June 19, 2025, issued by the Central Steering Committee for the development of science and technology, innovation, and digital transformation.
16:28 08/07/2025
Hanoi issues waste prevention program until 2035
Hanoi issues waste prevention program until 2035
Chairman of the Hanoi People's Committee Tran Sy Thanh signed Decision No. 3712/QD-UBND on July 8, 2025, issuing the City's Program on Anti-Wastefulness through 2035.
15:55 08/07/2025
Hanoi promotes public awareness of fire prevention
Hanoi promotes public awareness of fire prevention
Standing Vice Chairman of the Hanoi People's Committee Le Hong Son has recently signed and issued Official Dispatch No. 3877/UBND-NC dated July 3, 2025, regarding the implementation of Official Telegram No. 100/CĐ-TTg dated June 29, 2025, issued by the Prime Minister.
15:55 03/07/2025
Hanoi calls for greater efficiency in fire prevention and rescue
Hanoi calls for greater efficiency in fire prevention and rescue
Standing Vice Chairman of the Hanoi People's Committee Le Hong Son has signed and promulgated Official Dispatch No. 3886/UBND-NC dated July 3, 2025, regarding the implementation of the Law on Fire Prevention and Fighting and Rescue and Decree No. 105/2025/ND-CP of the Government under the new model.
15:55 03/07/2025
Hanoi steps up efforts on forest protection
Hanoi steps up efforts on forest protection
Vice Chairman of the Hanoi People's Committee Nguyen Manh Quyen has recently signed and promulgated Official Dispatch No. 3840/UBND-NNMT dated July 1, 2025, on strengthening forest protection management, forest fire prevention and fighting, and management of forestry land in Hanoi.
16:14 01/07/2025
Monthly allowance of $191 granted to digital transformation personnel
Monthly allowance of $191 granted to digital transformation personnel
The Government of Vietnam has set out a monthly allowance for personnel working in digital transformation, cybersecurity, and network safety roles.
16:12 01/07/2025